Dear owners, 

 

We would like to update you on the progress of Chalet Kashmir.
You can see new photos of the site at the end of this message.

Access to the chalets :
VRD, curbs and asphalt have been implemented for access to the chalets.

Painting :
The painter has finished his service and will return for the final details at the end of the project.

Parquet and tiles:
The parquet floor worker is in place and has carried out the resurfacing.
The laying of the parquet will begin on chalets D, then C, A and B.
The installation of the communication doors will follow.

The tiles and earthenware are being finished


Kitchens:

The kitchen designer is ready to intervene as soon as the parquet flooring work is finished.


Electricity and plumbing
:
The electrician carries out the fitting (installation of sockets and covers) of the chalets, and finishes the finishing of his electrical panels.
The plumber has started installing the furniture and bathroom vanity tops and will continue with the fitting work (taps, mixer taps, etc.)


Heating :
The resistance which was missing was put. The PACs are on site and are being prepared for commissioning.


We will regularly publish new photos of the construction site on your owner space.


Kind regards


La SCCV Chalet Kashmir